Implementation of Iowa DOT Pavement Management Optimization Model, 2000

Project Details
STATUS

Completed

START DATE

01/01/00

END DATE

04/30/01

RESEARCH CENTERS InTrans, CTRE
SPONSORS

Iowa Department of Transportation

Researchers
Principal Investigator
Omar Smadi

Director, CTRE

Co-Principal Investigator
Reginald Souleyrette

About the research

This project covers the activities required for the continued implementation and enhancement of the Iowa DOT pavement management optimization system. The work will cover all of the Iowa DOT interstate and primary (NHS and non-NHS) systems. Previous phases covered the evaluation and selection of the pavement management methodology. This phase covers new enhancements being made to the pavement management system, including managing the automated distress data collection contract, developing the GIS database, and providing continued support for the Iowa DOT pavement management activities.